The University of Tennessee at Chattanooga | IT Projects

Monthly Area Update - October 2019

Active Projects

Project Title Description Sponsor ≈ Completion
State Building 5th floor Move all of IT to the 5th floor of the State Building IT 63%
Lupton IT Infrastructure and AV Academics 49%
Mapp - Center for Professional Education Office Relocation Center for Professional Education 61%
Mapp - RCOB Entrepreneurial Center IT Infrastructure and AV RCOB 25%
Fine Arts Building IT Infrastructure and AV Academics 46%
VoIP - Phase I Replace copper phone system with voice over internet protocol system IT 50%
Ethos EIS CAS replacement IT 95%
DUO (Two-Factor Authentication) Implement DUO on campus for two-factor authentication IT 65%
Bandwidth Upgrade Increase bandwidth from 2x5Gb to 2x10Gb IT 97%
Migrate Domain Resources from UTC to CHA Domain Remove all resources from the legacy UTC domain and migrate them to the new CHA domain. IT 26%
IT Security - Secure Access Develop processes and procedures for deprovisioning users IT 85%
IT Security - Cyber Threat Protection Develop list of recommendations for disk encryption and sever hardening. SCCM patching. IT 70%
IT Security - Incident Response Develop incident template, update DRC, and identify response team IT 86%
IT Asset Management Plan Develop a comprehensive asset management plan from the time of purchase to disposal. IT 75%
Computer Refresh 2019 Campus computer replacement IT 71%
Software
Implementation: Star
Rez
System to manage housing
assignments
Housing 75%
Software
Implementation: TMA
System to manage inventory
and facilities work orders
Housing 40%
Software
Implementation: Team Works
Athlete engagement platform
integration with Banner
Athletics  75% 
Website Drupal Migration Environment build, configuration, migration of current pages from OU Campus to Drupal Communications and Marketing 25%
Fletcher Hall (floors 3 & 4) IT Infrastructure and Technology install Academics 47%
Fletcher Hall (floor 1) IT Infrastructure and Technology install Academics 37%
Tennis Center Cameras Install live streaming cameras at each court Athletics 50%
Police Dispatch Center IT Infrastructure and Technology install Safety and Risk 37%
EOC - Phase III IT Infrastructure and Technology install Safety and Risk 27%
UC Auditorium IT Infrastructure and Technology install University Center 43%
Multicultural Center IT Infrastructure and Technology install Office of the Dean of Students 50%
Hunter 208 IT Infrastructure and Technology install Academics 41%
UC Meeting Rooms IT Infrastructure and Technology install Academics 43%

Completed Projects

Project Title Description Sponsor ≈ Completion
Software Implementation:
Curriculog
System to manage curriculum changes and approvals
Academic Affairs Oct-19
Software Implementation:
Osnium
Case management and reporting software for sexual assault tracking
Women's Center Oct-19
Software Implementation:
Connect2
System to manage student recreation facilities and equipment
ARC Oct-19
Software Implementation: Create A Check
Provide ability to create checks for Accounts Payable
Accounting Services Oct-19
Website Refresh
Website clean-up, accessibility review, and dept page redesign
Communications and Marketing Oct-19