The University of Tennessee at Chattanooga | IT Projects

Monthly Area Update - January 2020

Active Projects

Project Title Description Sponsor ≈ Completion
State Building 5th floor Move all of IT to the 5th floor of the State Building IT 71%
Lupton IT Infrastructure and AV Academics 51%
Mapp - Center for Professional Education Office Relocation Center for Professional Education 70%
Mapp - RCOB Entrepreneurial Center IT Infrastructure and AV RCOB 43%
Fine Arts Building IT Infrastructure and AV Academics 50%
VoIP - Phase I Replace copper phone system with voice over internet protocol system IT 47%
Ethos EIS CAS replacement IT 95%
DUO (Two-Factor Authentication) Implement DUO on campus for two-factor authentication IT 65%
Migrate Domain Resources from UTC to CHA Domain Remove all resources from the legacy UTC domain and migrate them to the new CHA domain. IT 26%
IT Security - Secure Access Develop processes and procedures for deprovisioning users IT 85%
IT Security - Cyber Threat Protection Develop list of recommendations for disk encryption and sever hardening. SCCM patching. IT 70%
IT Security - Incident Response Develop incident template, update DRC, and identify response team IT 86%
IT Asset Management Plan Develop a comprehensive asset management plan from the time of purchase to disposal. IT 75%
Software
Implementation: Star
Rez
System to manage housing
assignments
Housing 75%
Software
Implementation: TMA
System to manage inventory
and facilities work orders
Housing 40%
Software
Implementation: Team Works
Athlete engagement platform
integration with Banner
Athletics 75%
Website Drupal Migration Environment build, configuration, migration of current pages from OU Campus to Drupal Communications and Marketing 25%
Fletcher Hall (floors 3 & 4) IT Infrastructure and Technology install Academics 49%
Fletcher Hall (floor 1) IT Infrastructure and Technology install Academics 40%
Tennis Center Cameras Install live streaming cameras at each court Athletics 40%
Police Dispatch Center IT Infrastructure and Technology install Safety and Risk 39%
EOC - Phase III IT Infrastructure and Technology install Safety and Risk 27%
UC Auditorium IT Infrastructure and Technology install University Center 98%
Multicultural Center IT Infrastructure and Technology install Office of the Dean of Students 50%
Hunter 208 IT Infrastructure and Technology install Academics 41%
UC Meeting Rooms IT Infrastructure and Technology install Academics 98%
Edney Building - 2nd Floor
IT Infrastructure
and Technology install
Office of
Research
7%
Classroom Refresh '20
Classroom technology
replacement
IT 86%
Computer Refresh '20
Campus computer
replacement
IT 9%
Interactive Maps
To enhance maps and
wayfinding for the UTC
website
Communications and Marketing 25%
LinkedIn Learning Integration
To integrate LinkedIn Learning
platform into K@TE for
employees
IT 25%