Capital Project Status Notes

February 10, 2009

 

Student Recreation Center

Status:               Construction

Current Task:    Finishing up exterior masonry and glazing, working 7 days a week to catch up.  Plans call for HVAC unit start-up in late February to begin drying out the building. 

 

Student Recreation Center Pool Addition

Status:               Design

Current Task:    Construction documents are complete with UT wrapping up mechanical review.  Should be in State Fire Marshal’s office by end of    February, bid in March. 

 

New Library Building

Status:               Design

Current Task:    Preliminary schematic design presented Feb. 2nd, floor plans to be presented in mid February.

 

Athletic Strength & Conditioning Center  (Lawson Center)

Status:               Construction

Current Task:    Building is substantially complete, with certificate of occupancy awarded 11/20.  Punch list being worked off.

 

Engel Intramural Development

Status:               Construction

Current Task:    Two fields are substantially complete.  Third field will be completed as a local project. Field lighting is being installed as weather permits.

 

Campus Elevator Upgrades

Status:               Construction

Current Task:    Work is substantially complete with punch list being worked off.

 

Metropolitan Building Renovation

Status:               Construction

Current Task:    Renovation underway with demolition 50% complete.  Asbestos abatement complete with exception of gypboard removal done through the general contract

 

Grote Hall Renovation

Status:               Construction

Current Task:    Asbestos abatement is complete. Drawings in State Fire Marshal’s office for review, UT completing final review.  Project to be bid ASAP.

 

Electrical Distribution Upgrade, Phase II

Status:               Construction

Current Task:    Project underway most underground work done over Christmas break.  Work in the Central Energy Plant and various buildings will take place through October.

 

UC Student Services

Status:               Design

Current Task:    Construction estimated at $830,000.  Drawings to be sent to Fire Marshal this month, bid in March.

 

Central Plant Boiler Replacement, Phase II

Status:               Design

Current Task:    Kick-off meeting with MEP Engineering held 12/4.  Schematic design underway.