Capital Project Status Notes

July 14, 2009

 

Student Recreation Center

Status:               Construction

Current Task: 

Certificate of Occupancy granted 7/2.  Punch list being worked off.  Grand opening set planned for 8/18.

 

Student Recreation Center Natatorium

Status:               Bidding

Current Task:

Construction documents complete, TFM office has approved plans.  Pre-bid conference set for 7/23, opening 8/6.

 

New Library Building

Status:                 Design

Current Task:

Schematic design approved, architects in design/development phase.  Soil sampling shows probable void that will determine foundation design.  Considering an early release site package to get work underway in early 2010.

 

Metropolitan Building Renovation

Status:                 Construction

Current Task:

Renovation well underway with all wall construction complete.  Awaiting HVAC equipment delivery in late August.

 

Grote Hall Renovation

Status:                 Construction

Current Task:

Asbestos abatement complete. Plans approved by TFM, bids opened in late May.  Funding issue resolved, contract notice-to-proceed set for 7/20.

 

Electrical Distribution Upgrade, Phase II

Status:                 Construction

Current Task:

Project nearing completion.  Change-over to new switches and transformers scheduled through the end of July.  Secondary feed to campus on EPB schedule.  

 

UC Student Services Renovation

Status:                 Construction

Current Task:

Bids opened with low bid for both floors approx. $150K over budget.  Proceeding with ground floor build for Admissions.  UT to disclose increased project costs. Upper floor Financial Aid space to be re-bid as a separate project.

 

Central Plant Boiler Replacement, Phase II

Status:                 Design

Current Task:

Construction documents nearly complete.  New feed from Central Plant to go underground on east side of garage.  Bid advertisement planned for August.

 

Scrappy Moore Field Improvements

Status:                 Design

Current Task:

Design for new drainage and partial synthetic turf well underway.  Plan to have project bid and ready to start construction at the end of 2009 football season.  Spending authority is $500k, Athletics would like to spend $300K.

 

Campus Entrance Improvements

Status:                 Design

Current Task:

Design underway, survey to be scheduled.  Plan to complete full design for east side of Mabel Gateway and prepare schematics for other entry features at Vine/Houston and Oak/Houston.

 

Fletcher Hall Financial Center

Status:                 Design

Current Task:

Program for trading center in former Bursar space completed, preliminary designs presented to donor.  To continue with design for Fletcher in Aug/Sept unless other location is eminent.  Target construction start immediately following Spring 2010.

 

ADA Improvements, Phase III

Status:                 Programming

Current Task:

Balance noted with 2008 funds, additional funds may be available from 2009.  Project programming must be determined working with Safety & Risk Management and ADA Committee.