Capital Project Status Report

July 2009

Capital Project Amount Funded (Authorized) Architect/ Engineers Design Start Date % Design Complete General Contractor Estimated Construction Duration Construction Start Date Construction Complete % Construction Complete
Student Recreation Center, Phase I $16,500,000 DHW/Franklin Oct 2003 100% Blaine Construction 20 months Jun 2007 Jul 2009 99%
Student Recreation Center, Phase II $7,300,000 DHW/Franklin Sep 2007 100%   12 months Aug 2009 Aug 2010  
New Library Building $48,000,000 DHW/Artech May 2008 30%   24 months Mar 2010 Mar 2012  
Metropolitan Building Renovation, Phase II $2,350,000 Charles King Architects Oct 2004 100% Pointe General Construction 10 months Nov 2008 Sep 2009 65%
Grote Hall Renovation $8,250,000 Artech Feb 2005 100% Pointe General Construction 17 months Jul 2009 Jul 2010 3%
Electrical Distribution Upgrade-- Phase 2 $2,700,000 MEP Engineering Oct 2007 100% Lawson Electric 12  months Oct 2008 Oct 2009 90%
UC Student Services Renovation $700,000 Planning Associates Jul 2007 100% Construction Consultants 5 months Jul 2009 Dec 2009 0%
Boiler Replacement Phase II $3,360,000 MEP Engineering Oct 2008 98%   12 months Aug 2009 Aug 2010  
Scrappy Moore Field Improvements $500,000 Earthworx May 2009 75%   3 months Nov 2009 Feb 2010  
Campus Entrance Improvements $250,000 Carol Johnson Associates Jun 2009 5%   4 months Dec 2009 Apr 2010  
Fletcher Hall          Financial Center $1,200,000 TWH Architects Jun 2009 5%   3 months May 2010 Jul 2010  
ADA Improvements     Phase III $175,000         TBD      
Total Capital Program $91,285,000