Home / Facilities Planning & Management / ProjectStatus...
| Capital Project Status Report |
| July 2010 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Capital Project |
Amount Funded (Authorized) |
Architect/ Engineers |
Design Start Date |
% Design Complete |
General Contractor |
Estimated Construction Duration |
Construction Start Date |
Construction Complete |
% Construction Complete |
| Student Recreation Center, Phase II |
$8,600,000 |
DHW/Franklin |
Sep 2007 |
100% |
Rentenbach Constructors |
20 months |
Sep 2009 |
Apr 2011 |
40% |
| New Library Building |
$48,000,000 |
DHW/Artech |
May 2008 |
85% |
TN Dirtworks Rouse Const. |
24 months |
Jan 2010 |
Jan 2012 |
7% |
| Grote Hall Renovation |
$8,250,000 |
Artech |
Feb 2005 |
100% |
Pointe General Construction |
12 months |
Jul 2009 |
Jul 2010 |
95% |
| UC Student Services Renovation- PhII |
$350,000 |
Planning Associates |
Jul 2009 |
100% |
Bradanna Construction |
4 months |
Jul 2010 |
Nov 2010 |
5% |
| Boiler Replacement Phase II |
$3,360,000 |
MEP Engineering |
Oct 2008 |
100% |
Interstate Mechanical |
12 months |
Jan 2010 |
Oct 2010 |
50% |
| Campus Entrance Improvements |
$250,000 |
Carol Johnson Associates |
Jun 2009 |
100% |
Pointe General Construction |
4 months |
Jun 2010 |
Sep 2010 |
5% |
| Metro Renovation, Phase II |
$4,600,000 |
TBA |
|
|
|
|
|
|
|
| Stagmaier Hall Housing Restoration |
$2,500,000 |
TBA |
|
|
|
|
|
|
|
| Fletcher Hall Financial Center |
$1,200,000 |
TWH Architects |
Jun 2009 |
25% |
|
On Hold |
|
|
|
| ADA Improvements Phase III |
$450,000 |
Planning Associates |
Mar 2010 |
15% |
|
|
|
|
|
| (ARRA) Academic Math Mall |
$400,000 |
TWH Architects |
Mar 2010 |
60% |
|
|
|
|
|
| (ARRA) Patten House Exterior Repairs |
$700,000 |
Franklin Architects |
Mar 2010 |
60% |
|
|
|
|
|
| (ARRA) Fire Alarm Upgrades |
$200,000 |
MEP Engineering |
May 2010 |
30% |
|
|
|
|
|
| (ARRA) Window Replacements |
$500,000 |
Artech |
Mar 2010 |
75% |
|
|
|
|
|
| (ARRA) Roof Replacements |
$600,000 |
Hefferlin + Kronenberg |
Mar 2010 |
60% |
|
|
|
|
|
| (ARRA) Restroom Upgrades |
$600,000 |
Planning Associates |
Mar 2010 |
50% |
|
|
|
|
|
| (ARRA) Bretske Hall Improvements |
$1,540,000 |
TBA |
|
|
|
|
|
|
|
| (ARRA) Maclellan Gym Improvements |
$1,350,000 |
TBA |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
| Total Capital Program |
$83,450,000 |
|
|
|
|
|
|
|
|