Facilities Planning & Management Capital Project Status Report July 2009 |
|||||||||
| Capital Project | Amount Funded (Authorized) | Architect/ Engineers | Design Start Date | % Design Complete | General Contractor | Estimated Construction Duration | Construction Start Date | Construction Complete | % Construction Complete |
| Student Recreation Center, Phase I | $16,500,000 | DHW/Franklin | Oct 2003 | 100% | Blaine Construction | 20 months | Jun 2007 | Jul 2009 | 99% |
| Student Recreation Center, Phase II | $7,300,000 | DHW/Franklin | Sep 2007 | 100% | 12 months | Aug 2009 | Aug 2010 | ||
| New Library Building | $48,000,000 | DHW/Artech | May 2008 | 30% | 24 months | Mar 2010 | Mar 2012 | ||
| Metropolitan Building Renovation, Phase II | $2,350,000 | Charles King Architects | Oct 2004 | 100% | Pointe General Construction | 10 months | Nov 2008 | Sep 2009 | 65% |
| Grote Hall Renovation | $8,250,000 | Artech | Feb 2005 | 100% | Pointe General Construction | 17 months | Jul 2009 | Jul 2010 | 3% |
| Electrical Distribution Upgrade-- Phase 2 | $2,700,000 | MEP Engineering | Oct 2007 | 100% | Lawson Electric | 12 months | Oct 2008 | Oct 2009 | 90% |
| UC Student Services Renovation | $700,000 | Planning Associates | Jul 2007 | 100% | Construction Consultants | 5 months | Jul 2009 | Dec 2009 | 0% |
| Boiler Replacement Phase II | $3,360,000 | MEP Engineering | Oct 2008 | 98% | 12 months | Aug 2009 | Aug 2010 | ||
| Scrappy Moore Field Improvements | $500,000 | Earthworx | May 2009 | 75% | 3 months | Nov 2009 | Feb 2010 | ||
| Campus Entrance Improvements | $250,000 | Carol Johnson Associates | Jun 2009 | 5% | 4 months | Dec 2009 | Apr 2010 | ||
| Fletcher Hall Financial Center | $1,200,000 | TWH Architects | Jun 2009 | 5% | 3 months | May 2010 | Jul 2010 | ||
| ADA Improvements Phase III | $175,000 | TBD | |||||||
| Total Capital Program | $91,285,000 | ||||||||