| Facilities Planning & Management |
| Completed Capital Projects |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Capital Project |
Amount Funded |
Architect/ Engineers |
Design Start Date |
% Design Complete |
General Contractor |
Estimated Construction Duration |
Construction Start Date |
Construction Complete |
% Construction Complete |
| Engineering, Math & Computer Science Bldg. |
$28,800,000 |
DH&W/Artech |
Sep 1998 |
100% |
T.U. Parks |
20 months |
Aug 2001 |
May 2003 |
100% |
| University Center Expansion |
$15,000,000 |
TWH/MEP |
Jan 2000 |
100% |
J&J Contractors |
18 months |
Apr 2002 |
Mar 2004 |
100% |
| Student Recreation Center, Phase I |
$16,500,000 |
DHW/Franklin |
Oct 2003 |
100% |
Blaine Construction |
20 months |
Jun 2007 |
Jul 2009 |
100% |
| Race-Hooper Renovation Phase I |
$1,370,000 |
Franklin & Associates |
Dec 2000 |
100% |
WDB Construction |
12 months |
July 2002 |
July 2003 |
100% |
| ADA Improvements & Upgrades, Phase I |
$812,000 |
Planning Associates |
Aug 2000 |
100% |
WDB Construction |
7 months |
August 2002 |
Jun 2003 |
100% |
| Central Energy Plant Distribution Expansion |
$1,300,000 |
MEP |
Sep 1999 |
100% |
T.S Raulston |
11 months |
Aug 2000 |
Jul 2001 |
100% |
| Hunter Hall HVAC Renovation |
$1,600,000 |
Planning Associates |
Oct 1999 |
100% |
Foster Construction |
12 months |
Jul 2000 |
Aug 2001 |
100% |
| Boling Apartments Renovation |
$3,500,000 |
Planning Associates |
Oct 2000 |
100% |
WDB Construction |
12 months |
Aug 2001 |
Aug 2002 |
100% |
| Roof Replacements 2002 |
$1,200,000 |
Charles King Architects |
Dec 2000 |
100% |
Ph1-ABC Roofing Ph 2&3-TBM |
12 months* |
Sep 2003 |
May 2004 |
100% |
| Electrical Distribution Upgrade-- Phase I |
$2,080,000 |
MEP Engineering |
Oct 2002 |
100% |
Adman Electric |
10 months |
Jan 2004 |
Nov 2004 |
100% |
| Building Exterior Repairs |
$1,860,000 |
Charles King Architects |
Nov 2002 |
100% |
Williams Restoration |
16 months* |
Apr 2004 |
Mar 2006 |
100% |
| Central Energy Improvements (Chiller #2) |
$1,950,000 |
MEP Engineering |
Sep 2003 |
100% |
Jake Marshall |
10 months |
Feb 2005 |
Dec 2005 |
100% |
| Campus Landscaping Improvements |
$1,600,000 |
Ross/Fowler Architects |
Oct 2004 |
100% |
P & C Construction |
12 months |
Apr 2006 |
Apr 2007 |
100% |
| Central Energy Improvements (Chiller #3) |
$2,000,000 |
MEP Engineering |
Sep 2005 |
100% |
Jake Marshal |
10 months |
Jul 2006 |
Jun 2007 |
100% |
| Roof Replacements |
$1,300,000 |
Planning Associates |
Sep 2005 |
100% |
Porter Roofing, P&C, TBM |
9 months |
Jul 2006 |
Jun 2007 |
100% |
| ADA Improvements & Upgrades, Phase II |
$500,000 |
Planning Associates |
Jun 2005 |
100% |
J&J Contractors |
7 months |
Dec 2006 |
Jun 2007 |
100% |
| Hooper Hall Renovation |
$1,475,000 |
Franklin & Associates |
Feb 2005 |
100% |
J&J Contractors |
9 months |
Dec 2006 |
Aug 2007 |
100% |
| Challenger Center Expansion |
$900,000 |
Derthick, Henley & Wilkerson |
Nov 2004 |
100% |
Winesett-Hill Constructors |
9 months |
Jan 2007 |
Sep 2007 |
100% |
| Campus Fire Alarm Upgrades |
$400,000 |
Planning Associates |
Nov 2004 |
100% |
Nabco Electric |
5 months |
Jun 2007 |
Nov 2007 |
100% |
| Doctors Building Roof |
$300,000 |
Derthick, Henley & Wilkerson |
Nov 2006 |
100% |
Porter Roofing |
4 months |
Mar 2008 |
Jun 2008 |
100% |
| Boiler Replacement |
$2,675,000 |
MEP Engineering |
Aug 2006 |
100% |
Jake Marshall |
15 months |
May 2007 |
Aug 2008 |
100% |
| Arena Video Upgrade |
$875,000 |
n/a |
Jan 2008 |
100% |
Daktronics |
4 months |
Jul 2008 |
Oct 2008 |
100% |
| Athletic Strength & Conditioning Center |
$3,260,000 |
TWH Architects |
Mar 2005 |
100% |
Pointe General Construction |
10 months |
Feb 2008 |
Feb 2008 |
100% |
| Intramural Development |
$1,300,000 |
King Design/ BWSC |
Nov 2007 |
100% |
Stein Construction |
6 months |
Jul 2008 |
Apr 2009 |
100% |
| Campus Elevator Upgrades |
$1,500,000 |
Planning Associates |
Nov 2004 |
100% |
Vega Corporation |
14 months |
Dec 2007 |
Apr 2009 |
100% |
| Electrical Distribution Upgrade-- Phase 2 |
$2,700,000 |
MEP Engineering |
Oct 2007 |
100% |
Lawson Electric |
12 months |
Oct 2008 |
Oct 2009 |
100% |
| Metropolitan Building Renovation, Phase II |
$2,350,000 |
Charles King Architects |
Oct 2004 |
100% |
Pointe General Construction |
12 months |
Nov 2008 |
Nov 2009 |
100% |
| UC Student Services Renovation- PhI |
$550,000 |
Planning Associates |
Jul 2007 |
100% |
Construction Consultants |
5 months |
Jul 2009 |
Jan 2010 |
100% |
| Scrappy Moore Field Improvements |
$540,000 |
Earthworx |
May 2009 |
100% |
Competition Athletic Surfaces |
3 months |
Feb 2010 |
Jun 2010 |
100% |
| |
|
|
|
|
|
|
|
|
|
| Total Completed |
$100,197,000 |
|
|
|
|
* Construction duration |
|
|
|