The costs in the table below are based on selected components for the fueling station, local utility costs, and quotes from vendors:
Operating Costs: |
|||
Water Purification |
|||
(Aqua Solutions RO) |
Water Consumed |
24 ft^3/month |
|
Unit cost of H20 |
$0.20/ft^3 |
||
Water Cost |
$4.89/month |
||
Cost of 3/4" meter |
$18.29/month |
||
Purification Cost |
$23.08/month |
$276.96/year |
|
Electrolyzer |
|
||
(Hogen 40) |
Hydrogen Produced |
2.27kg/day |
|
Power Consumption |
169 kWh/day |
|
|
Electrical Cost Per Unit |
$0.09/kWh |
|
|
Electrolyzer Cost |
$15.58/day |
$5686.70/year |
|
|
|||
Compressor |
|
||
(Three Diaphragm) |
Hydrogen Supplied |
2.27kg/day |
|
Electricity Consumed |
8 kWh/day |
|
|
Unit cost of Electricity |
$0.09/kWh |
|
|
Compression Cost |
$0.74/day |
$270.10/year |
|
Total Operating Costs |
$6233.76/year |
||
Daily Production = |
2.27 kg |
||
Yearly Production = |
828.55 kg |
||
Fuel Station Cost = |
$220,414 |
||
Annual Capital Cost = |
$38,274 |
Based on A/P for an equipment life of 10 years |
|
Annual Cost of Facility/Yearly Production |
$44,522 |
||
Cost of Hydrogen = |
$53.77/kg |
||